Carrefour Laval, Expansion
Since we were preselected as the steel structure manufacturer on this amazing project, we were
Since we were preselected as the steel structure manufacturer on this amazing project, we were
As a turn-key project, the real estate developer had the obligation to build a surface and
In the estimation of a project, the total mass, the overhead clearance between floors and the total
This ambitious project changed this building in which our prestigious Canadian hockey
The mandate obtained by Sofab as concept-assistance, was to build from sketches done by
In this project, for which Sofab participated in the elaboration of the concept in a
The construction challenge was defined by the complexity of the 230 feet (70 m) long span
The 4 slope orientations of the roof were the most complex element of this hotel. Some
This 60 feet-high (18 m) plane maintenance hangar, is made of thirty-eight (38) long span trusses,
This long rectangular building was constructed with more than 900 main and secondary trusses